Design Plan for Steel Structure Construction Organization

Time:[2023-7-27]  Hits:2045

1、 Project Overview


Construction unit:


Project Name:


Construction unit:


Construction structure:


2、 Construction preparation


2.1 Skill Preparation

 


1. Before the official start of construction, on-site skill briefing work will be carried out in conjunction with the Planning Institute. After reviewing and positioning the guide points, a construction wire point measurement and control network will be established before the start of construction.


2. Conduct on-site verification of skill documents, familiarize yourself with the content of the documents, and based on construction investigations, promptly submit problems in the planning to the planning unit for resolution. Together, make supplementary construction drawings according to construction needs.


3. Based on the construction site investigation, planning documents, and the requirements of the owner, prepare an implementation construction organization plan, organize and guide the construction.


4. Prepare a special construction plan based on the planning documents.


5. Organize the debris, garbage, etc. within the construction site boundary.


6. Arrange a construction team to enter the site and prepare for construction.


7. Preparation of construction personnel, equipment, and materials, as well as skilled management personnel for this project, with equipment in place to meet construction requirements.


8. Do a good job of pre job training and safety education, communicate with all parties together, contact material sources, and acknowledge the transportation routes.


9. Select and implement construction teams with construction skills and experience that can ensure project quality to undertake various construction missions


2.2 Data preparation


Before leaving the factory, the steel components should be inspected by the manufacturer in accordance with the relevant specifications of the manufacturing specifications and the requirements of the planning diagram, and quality reports and actual error values should be filled out. After the steel components are delivered to the structural installation unit, the structural installation unit will conduct re inspection or spot check based on the quality report of the manufacturing plant and the classification of the components according to their properties


2. Based on the construction drawings, calculate the quantity of each main consumption data (such as welding rods, welding wires, etc.) and connecting parts (such as high-strength bolts, ordinary bolts), make order arrangements, and acknowledge the arrival time


3. After the quantity of temporary support, steel structure assembly platform, scaffolding support, safety protection, and environmental protection equipment required for each construction process is recognized, they will be arranged to enter the factory for manufacturing and installation.


2.3 Primary equipment


In steel structure construction, the main machines commonly used include: AC/DC welding machine, C02 gas shielded welding machine, Bench grinder, wire rope, rigging, Dumpy level, etc.


2.4 Operating conditions


1. The joint review of various planning plans has been completed.


Based on the structural deepening drawings, verify the stress conditions of the components during the steel structure installation, scientifically predict their possible deformation, and take corresponding reasonable technical measures to ensure the smooth operation of the steel structure installation


The review of construction plans for each special type of work has been completed.


The reinforced concrete foundation has been completed and passed the acceptance.


Temporary electricity and water supply for construction are laid in place.


6. Mobilization of labor force


7. The construction equipment and devices have passed the debugging and acceptance.


The incoming acceptance inspection of 8 components is qualified.


3、 Steel structure construction process


3.1 Process flow


Preparation of components, equipment, and personnel → Setting out and inspection of lines (axis and elevation) → Acceptance of embedded bolts and treatment of foundation surface → Component centerline and elevation line → Installation of column and beam center structure → Initial and final tightening of high-strength bolts → Welding of column to column nodes → Spot welding of beams and columns and beam joints → Scattered component (corner support) devices → Device pressed square steel → Welding and bolt connection


3.2 Operation process


1. Steel structure lifting sequence


Steel structure lifting generally requires distinguishing the lifting operation area, and steel structure lifting is carried out together in parallel order according to the distinguished area. After the lifting of a certain area is completed, measurement, calibration, and initial tightening of high-strength bolts are carried out. After several areas are installed, the overall measurement, calibration, final tightening of high-strength bolts, and welding are carried out. After welding and retesting, proceed to the lifting of the next section of the steel column. And according to the actual situation on site, carry out the lifting and partial laying operations of this laminated steel plate.


2 bolt embedment


The accuracy of the column orientation depends on the accuracy of the embedded bolt orientation. Control the elevation error of embedded bolts within+ Within 5mm, the error in positioning the axis should be controlled within ± 2mm.


3 Steel column installation process


Section 1 Steel Column Hoisting


(1) Setting of lifting points


The orientation and number of lifting points are recognized based on the specific conditions of the steel column shape, section, length, and crane function. Generally, steel columns have good elasticity and rigidity, and the lifting point adopts a single point positive lifting. The lifting point is set at the top of the column, with the column body vertical and passing through the center of gravity of the column, making it easy to lift, align, and calibrate. When multiple components are assembled into expanded units on the ground for installation, the lifting point should be accounted for and recognized.


(2) Lifting method


1. In multi-storey and high-rise steel Structural engineering, steel columns are generally lifted by a single machine, and for special or overweight components, double machines can also be used.


2. When lifting, it is necessary to keep the steel column straight and try to reverse and straighten it without dragging the root. During the lifting reversal process, attention should be paid to preventing collisions with other components that have already been lifted, and the sling should have a certain effective height. When lifting the first section of the steel column, a protective sleeve should be added to the embedded anchor bolt to avoid damaging the thread of the anchor bolt when the steel column is in place


3. The first section of the steel column is installed on the column base. Before installing the steel column, the climbing ladder and hanging basket should be hung in the predetermined position of the steel column and firmly bound. After lifting in place, the foundation bolts should be temporarily fixed and the straightness should be checked. The two sides of the steel column are equipped with temporary fixing connecting plates. After the upper section of the steel column is aligned with the center line of the lower section of the steel column top, the connecting plates are temporarily fixed with bolts.


It is necessary to wait for the anchor bolts to be fixed before loosening the sling.


(3) Steel column proofreading


Steel column proofreading requires three tasks: adjusting the elevation of the column base, adjusting the axis of the column base, and proofreading the straightness of the column body. Throughout the entire process, measurement is the primary focus.


1. Column base elevation adjustment


After placing the steel column, use the nuts or elevation adjustment blocks under the column bottom plate to control the elevation of the steel column (because some steel columns are too heavy, bolts and nuts cannot bear their weight, so a height adjustment block - steel plate adjustment elevation - needs to be added under the column bottom plate). The accuracy can be controlled within ± 1mm. The gaps reserved under the column bottom plate can be filled with high-strength, slightly expanded, and non-shortened mortar using the grouting method. When adjusting the elevation of the column base plate using nuts, the strength and stiffness of the anchor bolts should be calculated.


2. Adjustment of column bottom axis in the first section


Alignment method: Without loosening the hook of the crane, align the four points on the column base plate with the control axis of the steel column and slowly lower to the planned elevation direction.


3. Correction of Column Body Straightness in the First Section


Use cable wind rope calibration method. Use two 90 ° Theodolite to straighten. During the calibration process, continuously fine tune the nuts under the column base plate until the calibration is completed. Screw on the two nuts above the column base plate. The cable wind rope is loosened without force, and the column body is in a free state. Then recheck it with a Theodolite. If there is a slight error, repeat the above process until there is no error, and tighten the upper nuts. The nut on the anchor bolt is usually a double nut, which can be welded firmly with the screw after the nut is tightened.


Weld the nut and screw firmly.


4. Adjustment of column top elevation and control of other structural steel column elevations


There are two methods for adjusting the top elevation of columns and controlling the elevation of other structural steel columns: one is to install according to the relative elevation, and the other is to install according to the planned elevation. Generally, relative elevation devices are used. After the steel column is lifted in place, the connecting ear plates connecting the upper and lower steel columns should be fixed with large hexagonal high-strength bolts, but they should not be tightened too tightly. After being lifted by a crane, the crowbar can adjust the gap between the columns. Measure the pre calibrated elevation values of the upper and lower column tops, and after meeting the requirements, use steel wedges and spot welding to limit the drop of the steel column. Considering the welding seam and compression deformation, adjust and control the elevation error within 4mm.


5. Section 2 Steel Column Axis Adjustment


To ensure that the upper and lower columns do not show staggered joints, try to ensure that the centerline of the upper and lower columns overlaps as much as possible. The center line error of the steel column should be adjusted within a range of 3mm each time. If the error is significant, it should be adjusted 2-3 times. The positioning axis of each steel column is absolutely not allowed to use the positioning axis of the next steel column. It should be led from the ground control line to high altitude to ensure that each steel column device is correct and prevent excessive accumulation of errors.


6. Section 2 Steel Column Straightness Calibration


The key to proofreading the straightness of steel columns is to pre check the relevant dimensions of the steel columns. The straightness error at the top of the lower steel column is a comprehensive result of the bottom axis, displacement, welding deformation, sunlight effect, straightness correction, and elastic deformation of the upper steel column. Partial errors can be eliminated by reserving straightness error values. When the reserved value is greater than the accumulated error value of the next column, only the accumulated error value is reserved. Otherwise, the reserved value is reserved, and its direction is opposite to the error direction. Empirical value measurement: The general weld seam shortening value between beams and columns is less than 2mm; The shortening value of the column to column weld seam is generally 3.5mm


4. Steel beam installation process


1. Steel beam device


Steel beam devices are generally lifted using tool type lifting lugs or binding methods. Before installation, the center symbol of the steel beam should be introduced to the end of the steel beam to facilitate temporary positioning according to the positioning axis of the column bracket during lifting.


2. Calibration of steel beams


Proofreading includes elevation adjustment, vertical and horizontal axis adjustment, and straightness adjustment. It is necessary to proofread the steel structure beam after the structure forms a stiffness unit.


3. Elevation adjustment


Use a Dumpy level to stand on the beam or a specially erected platform to measure the elevation of both ends of each beam, weighted average all the data, and calculate a standard value. Calculate the elevation adjustment values of each point based on the standard values.


4. Vertical and horizontal axis calibration


Use a Theodolite to lead the axis to the column, determine the distance between the center line of each beam and the axis, pull a long rope (or use a Theodolite) on the center line of the beam top, and use a chain block to adjust the beam ends one by one. After the longitudinal and transverse axes of the steel beam meet the requirements, recheck the span of the structural beam.


5. Straightness proofreading


Straightness correction: Hang a hammer ball from the upper flange of the beam and measure the horizontal spacing between the wire rope and the upper and lower parts of the beam web. Adjust again based on the inclination of the beam (a ≠ a ') to make a=a.


6. Special rust removal equipment is used for rust removal, and shot rust removal can improve the fatigue strength and corrosion resistance of steel. The hardness of the steel surface is also improved to varying degrees, which is conducive to the adhesion of the paint film without the need for additional coating thickness. The abrasive used for rust removal must comply with quality standards and process requirements, and the relative humidity of the construction environment should not exceed 85%.


The surface of the steel after rust removal must be cleaned with tools such as a brush before proceeding to the next process. If the surface of the steel after rust removal is qualified and has returned to rust before applying primer, it needs to be re rust removed.


7. Paint


After passing the inspection of rust removal on the steel, the first layer of primer is applied on the surface. Generally, after the rust removal is completed, it is stored in the factory and can be coated within 24 hours. If stored outside the factory, the primer should be painted on duty. The paint should be applied in accordance with the planning requirements. After the first coat of primer is dry, the intermediate and top coats should be applied to ensure that the thickness of the coating meets the planning requirements. The paint should be evenly applied without sagging during the brushing process.


4、 Key points of quality acceptance


1 base and support surface


The positioning axis of the building, the positioning axis and elevation of the columns on the foundation, the specifications and orientation of the anchor bolts (anchor bolts), and the fastening of the anchor bolts (anchor bolts) should meet the planning requirements.


The fastening should meet the planning requirements.


2 Devices and proofreading


1. Steel components should comply with planning requirements and regulations. The deformation and coating detachment of steel components caused by transportation, stacking, and lifting should be corrected and repaired.


2. For nodes that require top tightening, the touch surface should not be less than 70% tight, and the maximum edge gap should not be greater than 0.8mm.


3. The surface of the steel structure should be clean, and the primary surface of the structure should be free of scars, mud, and other dirt.


When the steel component is installed on a concrete column, the error between its support center and the positioning axis should not exceed 10mm


5. Steel platforms, ladders, and railing devices in multi-layer and high-rise steel structures should comply with the current national standards of "Fixed Steel Vertical Ladders" (GB4053.1), "Fixed Steel Inclined Ladders" (GB4053.2), "Fixed Protective Rails" (GB4053.3), and "Fixed Steel Platforms" (GB4053.4).


5、 Product protection


1. High strength bolts, studs, welding rods, welding wires, etc. are stacked on shelves in the warehouse, with a maximum of four layers of stacking.


2. The stacking of steel components requires the site to be flat, sturdy, clean, dry, neatly stacked, with sleepers underneath, and to be resistant to deformation and rust.


3. It is not allowed to weld or cut completed components arbitrarily, or stack objects in the air. Welds and node plates that have been completed and inspected as qualified should be immediately sorted out and sealed as required.


When lifting the steel structure into position, it should be slowly lowered and should not collide with the already installed steel structure.


5. Carefully manage the manufactured steel columns, etc., to prevent the unreasonable placement of cushion base points from bending and deformation.


6、 Environmental and occupational health and safety control measures


1 Environmental control measures


1. When welding, steel pipes are used to set up protective railings, and colored cloth is used to surround the railings to prevent the exposure of arc light and welding smoke and dust.


2. Waste generated during and after construction should be recycled and treated.


2 Occupational Health and Safety Measures


1. It is necessary to include the safety skills and measures for operations, as well as the required equipment, in the construction organization plan of the project.


2. Corresponding responsibility systems should be established for unit project construction. Before construction, safety skill education and disclosure should be carried out step by step, and all safety skill measures should be implemented. Construction should not be carried out without implementation.


3. It is necessary to inspect the facilities and equipment used in high-altitude operations before construction, and only after acknowledging their integrity can they be put into use.


4. It is necessary for climbing and suspended operators to hold a certificate and undergo regular professional knowledge assessment and physical examination. It is necessary to wear a safety helmet, fasten a seat belt, wear anti slip shoes, and carry a tool bag when on duty.


5. The high-altitude operation area should have clear signs and be guarded by dedicated personnel. Personnel unrelated to lifting are prohibited from entering. During crane operation, no one is allowed to stand within the rotating radius of the boom.


6. When transporting lifting components, it is prohibited to stand on the components to command and place materials and tools.


7. It is necessary to bind the components firmly, and the lifting point should pass through the center of gravity of the components. When lifting, it should be stable to prevent vibration or oscillation.


8. When working at heights, safety nets need to be installed to prevent accidents caused by personnel, materials, and tools falling or flying out.


9. All objects that may fall from the construction site should be removed or fixed first. The materials used in high-altitude operations should be stacked steadily and not obstruct passage and loading and unloading.


10. When conducting high-altitude operations on rainy and snowy days, it is necessary to take reliable anti slip, cold and freezing measures. Water, ice, frost, and snow should be promptly removed. Before construction, go to the local meteorological department to understand the situation and take measures to prevent typhoons, rain, freezing, cold, and high temperatures. Before and after the snowstorm and typhoon rainstorm, the safety facilities for high-altitude operation shall be checked one by one, and the problems found shall be improved immediately.


11. During the process of structural installation, it is not allowed to operate in the same straight direction when each type of work is engaged in vertical crossing operations. The orientation of the lower level operation needs to be outside the radius of the possible falling range recognized according to the height of the upper level; When the above conditions are not met, a safety protection layer should be set up.


7、 Issues to pay attention to


The quality of pre assembled steel components should meet the planning requirements and quality specifications. The length dimensions of components such as columns, beams, and supports should include deformation values such as welding shortening allowance.


The detection of device errors should be carried out after the structure forms a spatial stiffness unit and is connected and fixed.


When installing 3 devices, it is necessary to control the construction load of the platform flooring, and the construction load must not exceed the bearing capacity of beams, deck slabs, platform flooring, etc.


Only after the installation, welding, and bolting of all components of each column are completed and accepted can the positioning axis of the previous column be measured from the ground.

Copyright:佛山市勝邦鋼結(jié)構(gòu)有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號(hào)
主站蜘蛛池模板: 武汉印刷厂_为企业提供宣传单页彩页印刷_武汉折页印刷_海报设计印刷与制作 - 武汉泽雅印刷公司 | 武汉防雷检测_防雷工程设计施工_防雷设备材料_湖北普天科技有限公司 | 联智通达_工控一体机_工业触摸一体机_工业一体机_工业触控一体机_POS机主板_工控主板_国产化主板_RK3588主板厂商-联智通达 | 九江赛璐珞实业有限公司-赛璐珞板,赛璐璐板材,PVC装饰膜,PVC片材,醋酸纤维胶板_多彩装饰材料生产厂家 | 回收求购煤矿机械矿山设备,二手液压支架,刮板输送机-华建智能再生资源公司 | 景德镇芳然装饰有限公司| 无线对讲系统-海能达对讲机-广州中达慧通科技有限公司 | 压滤机专用泵|柱塞泥浆泵|咸阳华星泵业有限公司 | 整体滤板模板-S型塑料滤砖-MBBR生物悬浮球填料-微孔曝气器-大恒环保科技 | 温湿度变送器_pm2.5传感器_湿敏电阻_二氧化碳传感器_甲醛传感器-美特瑞科技 | 环球医网 | 带来健康生活... | 铁三角话筒-思美音频处理器-艾伦赫赛数字调音台-北京盛世音盟电子科技有限公司 | 环保白电油_甲醇_二价酸酯DBE_防白水-【名亿新材料】 | 扬州市德友线缆有限公司-业从事高端特种线缆研发、制造、销售与服务。 | 盆底肌修复仪器-产后康复脉冲磁训练仪-南京佳澜健康管理有限公司 | 五金冲压件生产厂家_加工五金拉伸件-沧州浚鼎机械制造有限公司-沧州浚鼎机械制造有限公司 | 无塔供水_全自动无塔供水设备_石家庄工泉水处理_无塔供水器 | 聚焦吉林-城市晚报官方网站 | 云南万通汽车学校【官方网站】| 济宁卡尔迪机械制造有限公司_铁路换枕机_升降驾驶室_挖机加高底盘_加长臂 | 自动化贴标机_套标机_圆瓶贴标机厂家_大为机械 | 小耳朵电源_安防监控电源|小耳朵官网|电源适配器|摄像机电源|开关电源|小耳朵监控电源 | 双合金_注塑机_螺杆|炮筒|料管|料筒-广东海驰德塑胶机械有限公司 | 游戏加速器-极迅互联加速器-更快更稳的网游手游免费加速器 | 液态硅胶制品厂家_液态硅胶包胶加工_LSR液态硅胶模具厂_液体硅胶注射成型_广东盈泰 | 长沙物流公司|湖南货物运输公司|长沙第三方物流公司-国联物流 湖南第三方物流专家 | 展会设计搭建-展厅设计施工公司-展位展台设计搭建-深圳鼎泰展览 展柜设计定制-品牌展柜订做-展柜制作厂家「广州嘉艺展柜」 | 长春衡宇机械 食品干燥机 微波灭菌机 连续真空干燥机-干燥行业先进企业 | 河北徐工鲲鹏工程机械有限公司无锡分公司 | 强德防盗门-防盗门厂家-中国防盗门十大品牌-强德门业 - 浙江臻品工贸有限公司 | 南京叉车|电瓶叉车|电动叉车|电动堆高车|电动搬运车-南京诺嘉机械 | 气象站_校园气象站_自动气象站_光伏气象站-山东万象环境科技有限公司 | 无人叉车|智能无人叉车|智能AGV叉车|激光叉车AGV厂家_江西丹巴赫机器人股份有限公司 | 微型直流减速电机-直流永磁电机-直流永磁电机厂家-微型直流减速电机定制-东莞市鑫辉传动科技有限公司 - 鑫辉传动科技 | 青岛除甲醛公司|青岛甲醛治理|青岛除甲醛|甲醛检测|光触媒除甲醛|装修除味除甲醛|新房除甲醛|青岛室内环境污染检测治理|青岛闪洁环保科技有限公司官网 | 中标通国际认证(深圳)有限公司-知识产权管理体系认证-湖北知识产权贯标 | 可燃气体报警器-有毒有害气体检测仪-气体检测分析系统-宁波市高品科技有限公司 | 云梯车|云梯搬家车|工程高空上料车|云梯登高车价格|视频|图片-专汽之家 | 江苏鹤心食品有限公司-茶叶_果浆果酱_固体饮料| 烘干机_回转窑_破碎机_制砂机_洗砂机_球磨机-瑞光金属制品 | 泥浆振动筛|卧式泥浆搅拌器|泥浆离心机|泥浆处理固控设备_沧州宏宇石油机械有限公司 |